The purpose of this modification is to revise paragraph (vi):
STATEMENT OF WORK
Pressure Wash Multiple Buildings, W.O. # 91051
Pope AFB NC
Work Description
A. Contractor shall chemically abate and clean mold and mildew stains and streaks from buildings and roof shingles using Non-Toxic, bio-degradable chemicals approved by EPA.
B. Contractor supplies all tools, equipment, materials, supplies and labor, verifies all requirements of proper handling, applications, abatement and disposal of chemical solutions and contaminates to affected areas.
C. Contractor must provide chemicals listing, as to exactly what is to be used on Installation.
Note: All building & sign measurements are perimeter of structure
D. Work to be completed at the following facilities on Pope:
1. Bldg 294, âDormitoryââColumns in front of dorm. 19 each
(15 columns 12â in height / 4 columns 20â in height)
2. Bldg 315, âComptrollerââEntire bldg. and surrounding brick work
(540â, 2-story bldg)
3. Bldg 313, Brick enclosure wall surrounding HVAC unit (60â, 6â in height)
4. Bldg. 317, âChapelââBrick sign, in front of facility (24â, 5â in height)
5. Bldg 307, âHospitalââBrick wall in front of Clinic separating main facility from Flight Medicine (64â, 5â in height, plus brick archway 10â, 12â in height)
6. Bldg 308, âMPFââEntire building (640â, 2-story bldg)
7. Bldg 402, âGymââEntire facility to exclude new addition (580â, 3-story bldg)
8. Bldg 372, âTheaterââEntire facility ( 540â, 3 story bldg)
9. Bldg 352, âDining HallââBrick walls surrounding dumpsters (240â, 10â in height)
10. Bldg 378, âSecurity Forces BldgââEntire building (420â / 1-story bldg)
11. Bldg 255, âArmy Corps of EngineersââShingle roof only (300â / 1-story bldg)
12. Bldg 219, âEntrance to General Officer QuartersââBrick retainer walls at entrance (280â, 2â in height)
13. Bldg 900, âCommand PostââBrick/block wall in front of side parking lot (3 separate brick walls totaling 128â, 12â feet in height)
14. Bldg 708âBlock wall surrounding fuel tank (60â, 8â in height)
15. Bldg 110, âMain Gate Visitors CenterâBrick walls, 6 each (all walls total 300â, 4â in height)
16. Bldg 614âRear brick/block wall only (130â, 10â in height)
17. Bldg 519, âReadiness CenterââHigh bay, shingle roof only (480â)
18. Bldg. 140, âCombat ControlââBrick sign only (32â, 5â in height)
19. Bldg. 193, âITT OfficeââBrick planters (390â in overall length of 5 brick planters, 2â in height)
20. Armistead Gate, all brick retainer walls (200â overall length of 4 retainer walls, 4â in height)
21. Hillcrest Housing entrance brick sign (34â, 4â in height)
22. Cardinal Heights Housing entrance brick sign (34â, 4â in height)
23. Bldg. 134âPerimeter wall (280â, 8â in height)
24. Bldg. 764âBlock wall in parking lot and building sign (wall & sign total 526â, 6â in height)
WORKMANSHIP: All workmanship shall comply with standards and practices that are common to the trade.
CLEAN UP: Contractor is responsible for returning the work site and surrounding area to the condition in which they were found. The Contractor is required to properly dispose of all materials/parts that he moves.
NOTE TO CONTRACTOR: All work will be completed within 30 calendar days following the awarded date of this contract. Exception will be handled on a case-by-case basis. Changes and or modifications must have prior approval from the Contracting Officer. NO OZONE DEPLETING MATERIALS WILL BE USED.
WARRANTY: The contractor will guarantee all workmanship for a period of one year from completion of work. The contractor is responsible for any damages caused to government facilities.
The solicitation due date has been changed to Tuesday, 10 May 2005, at 4:00p.m. EST.
All other terms and conditions remain the same.