The following question was received concerning this solicitation:
Request a clarification on the quantities for levee removal on the above mentioned project. Do we use the areas highlighted on the site maps as a basis for our bid, or do be base our bid on an as seen basis, in other words would we be required to remove levees outside of the highlighted areas?
ANSWER: The maps have been marked with the areas from which levees are to be removed. Levees in other areas are NOT a part of this solicitation.