Work shall consist of roadway reshaping including obliterating existing ditchline by filling in with excavated, compacted material narrowing existing roadbed width, outsloping roadbed including existing turnouts, crushing and covering pipe inlets of culverts being abandoned in place, roadside clearing, removal of downdrain structures, elbows, and drop inlets, constructing diversion dips, producing, hauling, and placing riprap at dip locations, excavating benches at some riprap apron locations to accomodate stable placementof riprap, hauling and placing government furnished aggregate, and hydraulic seeding and mulching. Pit development/cleanup and haul route maintenance is also included. Project is located on the Klamath National Forest, Siskiyou County, CA. Price range is $100,000 to $250,000. Estimated start date is July 10, 2002 with a contract time of 53 days. Solicitation documents will be available for download on this website on or about May 22, 2002.