Federal Bid

Last Updated on 10 Sep 2021 at 3 PM
Solicitation
Alcova Wyoming

WY FLAP 407(1) Kortes Road

Solicitation ID 6982AF21B000026
Posted Date 10 Sep 2021 at 3 PM
Archive Date 10 Oct 2021 at 4 AM
NAICS Category
Product Service Code
Set Aside No Set-Aside Used
Contracting Office 6982af Central Federal Lands Divisi
Agency Department Of Transportation
Location Alcova Wyoming United states 82620

THIS PROJECT WILL BE ADVERTISED AS FULL AND OPEN

THIS IS NOT A REQUEST FOR BID - PLANS AND SPECIFICATIONS ARE NOT AVAILABLE.

PROJECT NUMBER:  WY FLAP 407(1)

PROJECT NAME:  Kortes Road

PROJECT DESCRIPTION:   The Kortes Road project is a minor widening/reconstruction, resurfacing, restoration, and rehabilitation (3R+) project in Natrona County, WY (approximately 30 miles west of Casper, WY). The proposed route is 7 miles long, generally extending from the intersection with Natrona County Road 408 northeast to Alcova, WY. The route is used primarily as recreational access to Alcova Reservoir and Pathfinder Reservoir, as well as the Miracle Mile along the North Platte River.  The existing pavement is fatigued and nearing the end of its serviceable life. The county owns and maintains Kortes Road.     

SIGNIFICANT QUANTITIES:

Schedule A:

  • 20401-0000 Roadway Excavation: 11,500 CUYD
  • 30101-000 Aggregate Base: 11,500 TON
  • 30401-5300 Full Depth Reclamation, Method 2, 6-inch Depth: 6.821 Mile
  • 40101-5600 Asphalt Concrete Pavement, Gyratory Mix, ½-Inch or ¾-Inch Nominal Maximum Size Aggregate, 0.3 to <3 Million ESAL: 18,000 TON
  • 61701-4500 Guardrail System MGS, Type 2, Class A Wood Posts: 4,550 LNFT
  • 62515-3000 Mulching, Hydraulic Method, Bonded Fiber Matrix: 30 ACRE

MISCELLANEOUS:   General scope of improvement is to pulverize the existing section and place a 3-inch HACP section on the reclaimed 6 inches of pulverized existing material, raising the vertical profile of the road by 3 inches for the entire 7-mile corridor and minor shoulder widening (1-foot paved). Proposed improvements also include minor alignment and grade changes, signing and striping enhancements, drainage improvements, and other safety improvements

COST RANGE:  The proposed project is estimated at a cost between $6,000,000 and $7,000,000.

CONSTRUCTION DURATION:  Construction is anticipated between May 2022 and October 2022

ADDITIONAL INFORMATION:

Anticipated Advertisement:  Late September 2021

Anticipated Bid Opening:  Late October 2021

Anticipated Award: Mid November 2021

Bid Protests Not Available

Similar Past Bids

Alcova Wyoming 24 Jun 2021 at 11 PM
Alcova Wyoming 22 Oct 2021 at 10 PM
Alcova Wyoming 20 Oct 2021 at 9 PM
Alcova Wyoming 01 Nov 2021 at 3 PM
Alcova Wyoming 19 Oct 2021 at 6 PM

Similar Opportunities

Billings Montana 24 Jul 2025 at 6 PM
Location Unknown 13 Jul 2025 at 9 AM (estimated)
Billings Montana 11 Jul 2025 at 9 PM
Billings Montana 11 Jul 2025 at 9 PM
Billings Montana 17 Jul 2025 at 7 PM