The Work consists of rehabilitation of two existing 18-inch diameter techite wastewater pipelines that are located within an environmentally sensitive canyon environment, construction of temporary access roads, clearing and grubbing, adherence to environmental permitting requirements, temporary stream crossing installations. construction of three pressurized access structures, modifications to an existing concrete flow splitter structure, abandonment of existing cleanout structures, modification to an existing rock trap structure, and pipeline modifications at an existing flow meter station, per specifications.