The Contractor shall furnish all necessary labor, materials, services, equipment, supplies, power, accessories, facilities and such things as are necessary, except as otherwise specified, to perform repairs and alterations to the USCGC HAWK (WPB 87355) Specifications for Dockside Repairs FY 2015 , dated 17 November 2014/Rev-0.
Period of Performance is 31 March 2015 through 2 May 2015.
Work covered by this contract shall be completed within thirty-two (32) calendar days from the date the vessel becomes available to the Contractor.
The award is subject to the availability of funding per FAR 52.232-18 (APR 1984).
Quotations are due by 7 January 2015, 3:00 PM EST.
Bid Protests Not Available