Posted Amendment 0002 14 SEP 2023, Seed Task Order CLIN 0006, Concrete Curb Construction Quantity and Unit Revised. See red font. (Revised A21. Solicitation Pg 1-126)
Posted Amendment 0001 8 SEP 2023, no questions/answers submitted, site vist log, bid opening webex information and correction on A21. solicitation in red font for date of submission.
Allow for sending multiple emails for submission labeling 1 of X, 2 of X, due to size and USACE server restriction on email size allowance.
Revised 22 AUG 2023 1:35PM CST: Title, A21. Solicitation Pg 1-126
Bids submitted NLT September 21, 2023 at 9:00 AM CST
Site Visit September 6, 2023 at 10AM CST- See Solicitation For Details
In accordance with FAR Subpart 14.3, bids shall include the following:
. Complete Entire Solicitaiton SF1442 Document, Sign As Required.
. Complete Representations & Certifications Form
. Complete FAR Provision and Clause Fill-In Information.
. Complete Pre-Priced Line Items Base Unit Price and Extended Amount.
. Complete First Task Order- Seed Order Unit Price and Extended Amount.
. Submit a SF 24, Bid Bond Guarantee, In Accordance With FAR 52.228-1 of this solicitaiton.
(Note: A21. Solicitation File is very large, it has been broken up into mutlple sections to be uploaded)