RECOVERY (ARRA) - The work consists of the Installation of four separate septic systems at the El Cariso Hot Shot Camp and the Replacement of the existing septic tank at the Silverado Fire Station.
This project is funded by the American Recovey & Reinvestment Act (ARRA).
Amendment 3 is included with this posting and Attachments 1 - 3.
The purpose of this Amendment 3 is to 1) Revise and Replace the Schedule of Items (Att 1), 2) add Specification Section 01505 - Mobilization (ATT 2); Specification Section 02050 - Demolition (Att 3); Specification Section 03100 - Concrete Formwork (Att 4); and Specification Section 03200 - Concrete Reinforcement (Att 5) of this Amendment, add to the Request for Quote Documentation; and 3) Answers to Vendor's Questions
that follow:
Q)Can you tell me how the material testing and
special inspections will be handled for the
Recovery Cleveland National Forest Wastewater
Improvements Project? Via the owner or the
Contractor?
A)All material testing and special inspections
and quality control will be the responsibility of
the contractor.
Q)Are your requiring cleanouts every 50 feet?
A)Cleanouts will be required to be installed AS
SHOWN ON CONTRACT DRAWINGS and where the
Uniform Plumbing Code 2006 with California amendments,
requires they be installed for this type of sewer
installation.
BID SUBMITTAL DATE IS CHANGED FROM: June 2, 2010,
2:00 PM Pacific Time TO: June 4, 2010, 2:00 PM Pacific Time
PLEASE FOLLOW SECTION L BID SUBMITTAL
INSTRUCTIONS IN THE REQUEST FOR QUOTE PACKAGE.
THE ONLY INFORMATION CHANGE IS THE BID SUBMITTAL
DATE. BE SURE AND SUBMIT AMENDMENTS 1-3 SIGNED
AND DATED WITH YOUR BID PACKAGE DOCUMENTS.
Period of Performance: 06/15/2010 to 08/20/2010
Bid Protests Not Available