THIS IS NOT A REQUEST FOR BID - PLANS AND SPECIFICATIONS ARE NOT AVAILABLE
PROJECT NUMBER: NM BR AAO ELBU(1)
PROJECT NAME: Elephant Butte Historic Roads
PROJECT LOCATION:
The Elephant Butte Dam approximately 4 miles east of Truth or Consequences, New Mexico, in Sierra County. The Elephant Butte Lake State Park which is managed by NM State Parks under a lease agreement with the U.S. Bureau of Reclamation. The project is located at the southern end of the Elephant Butte Reservoir and includes the Damsite area and Paseo del Rio. The Damsite area includes visitor amenities, a day use area, camping, casitas, and houses to rent. Paseo del Rio offers campsites, river access, hiking and biking trails, and historic information boards. Roads within the historic district also provide access to the largest marina at Elephant Butte Reservoir.
SCOPE OF THE WORK:
The project will use asphalt and aggregate base to resurface, restore, and rehabilitate multiple road segments within the Elephant Butte Historic District including: Dam Site Winding Road A/B, Ruins Road, Hospital Canyon Road A/B, Dam Site Entrance Road, unpaved Dam Site Marina Entrance Road, and Paseo Del Rio Campground Access Road.
The Paseo Del Rio River Access Road has native surfacing but will be improved with aggregate surfacing. 6 paved parking lots will be rehabilitated and repaved. 4 additional gravel/native/paved parking lots will be rehabilitated with aggregate surfacing.
This project is separated into a base Schedule A, along with two alternates, Option X and Y, to maximize the work that can be completed with the available funds.
Schedule A Includes:
Hospital Canyon Road A and B
Dam Site Entrance Road
Winding Road and Approach Roads
Paseo Del Rio Campground Access Road and Approach Roads
Dam Site Upper East and Upper West Parking
Dam Site Recreation Area Restaurant parking and Overflow Parking
Paseo Del Rio Recreation Area Highway 51 River Access Parking
Paseo Del Rio Recreation Area Campground Comfort Station Parking
Old Fish Hatchery Parking
Winding Road Parking
Option X includes:
Ruins Road
Option Y includes:
Dam Site Marina Entrance Road (concrete)
Dam Site Marina Entrance Road (unpaved)
Dam Site Marina South Parking
PRINCIPAL WORK ITEMS:
Schedule A
8,500 Cuyd Roadway Excavation
8,000 Cuyd of Waste
21,800 Sqyd Seeding and Mulching each
1 LPSM of temporary traffic control
Option X
4,000 Sqyd Prime Coat, Method 1
4,730 Ton, Aggregate Base
4,200 Sqyd Seeding and Mulching each
Option Y
3,000 Cuyd Roadway Excavation
3,000 Cuyd of Waste
4,000 Tons of Roadway Aggregate, Method 2, Surface
4,000 Sqyd of Prime Coat, Method 1
6,000 Sqyd Seeding and Mulching each
1 LPSM of temporary traffic control
DISCLOSURE OF MAGNITUDE: The estimated price range is between $7,000,000 and $10,000,000.
This is set-aside for HUBZone small business concerns.