The site of the work is located within Bow Street and Kent Avenue near the Brooks Street corridor and along Regent Street near the Brooks Street corridor in Missoula, Montana. The work generally includes installing approximately 12,240 square feet of new sidewalk, 1,180 lineal feet of new curb, 2,750 square yards of new asphalt replacement, drainage improvements, and associated demolition, excavation, signing, striping, surface restoration, and related work in accordance with the Plans and Specifications. The project is funded by the Missoula Redevelopment Agency and is subject to all applicable state and local regulations as indicated within the specifications. All work must be substantially complete within 60 calendar days after the commencement date stated in the notice to proceed. Notice to proceed is flexible with the latest start date of August 16, 2020, to meet a completion date no later than October 15, 2020.