The Work includes the following major items: The upsizing of approximately 1,603 LF of existing 10” reinforced plastic mortar gravity sanitary sewer to 12” PVC, the installation of approximately 52 LF of new 8” DIP and 53 LF of new 8” PVC sanitary sewer, and approximately 915 LF of new 10” PVC relief sanitary sewer with 11 manholes and the rehabilitation of 1 existing manhole. On Tuesday December 1st, 2020 at 9 A.M. local time, a Pre-Bid conference will be held via teleconference. To attend, please register in advance for this meeting: https://cbre.zoom.us/meeting/register/tJAqcOqprjooH9xqkTUUqZDiMwcoX-1UZlMk.
Bid Protests Not Available