The work consists of furnishing all labor, materials, tools, equipment, and incidentals as required by the plans (Drawing Number 16-08A, Sheets 1 through 4, Specifications, and Contract Documents). The general items of work include, but are not limited to: construction of approximately 450 feet of an asphalt concrete pavement bike lane and adjacent decomposed granite equestrian trail, with an approximately 200 foot section of combined equestrian/bike brick pavers pathway, the removal of a pepper tree and section of a concrete swale, minor grubbing and grading, installation of modified driveway approach, sidewalk and pavement repair, minor striping, and the placement of trail and directional signage, per specifications.
Bid Protests Not Available