COMING SOON Lititz, PA - Lancaster Airport - Rehabilitate Runway 8-26, Ph. V (Bid Package 3) (21010) Runway 8-26 will be rehabilitated to improve drainage, line of sight and other non-standard conditions. This is the third of four construction phases. The project will include the following items and approximate quantities: 1. Milling: 35000 SY 2. Variable Depth P-401: 12600 TN 3. Airfield Pavement Reconstruction: 2750 SY 4. RSA Grading: 17500 CY 5. Drainage Pipe Installation: 2800 LF 6. FAA Cable Relocation: 2000 LF