Questions and Answers:
1. Is this acquisition being conducted using FAR 13 or 15? FAR 13
2. When will the Government provide answers to interested vendor's questions? When the government can reasonably formulate an answer
3. How many ECP's require manning? Cannot disclose this information
4. How many towers require manning? Cannot disclose this information
5. How far is the guard force LSA from the Post? Unknown, COP is still under construction
6. a. Will the Government allow prime vendor hat do not hold a private security license with the Afghan MOI to bid on this RFP? Anyone can bid however, in order for a contract to be awarded the contractor must be on the approved Minstry of Interior List.
b. Will a prime venedor's partner's past performance be weighed the same as the prime vendor's? See 52.212-2 Addendum, Past Performance is considered a subfactor and is weighed neutral, pass, fail
7. Will the Government remove the "no identifying contractor information" on other than the Cover Page of the RFP requirement? Yes
8. What is the limit of the proposal Limitation? See page 3, 5 MB
9. Are there labor categories/positions that are considered by the Government to be key personnel? Site Manger & Shift Supervisors
10. Does the Government plan to expand the size of this contract throughout its period of performance? Unknown
11. Please provide a list of hazardous materials that the contractor will be required to be handled? Hazardous materials are handled on an as needed basis
12. Question not clear; However, the Ministry of Interior PSC license is not needed until contract award
13. What is the page limit of Volume I- Technical Capability- 5 MB for entire proposal
14. Have any amendments been issued? NO
15. Therefore, may offerors simply state that they have completed their respresentations and certifications via ORCA? YES, and will be verified prior to contract award
16. What level of English Comprehension are these interpreters required to process? Question does not apply to this RFP
17. When can interested vendors conduct site visits? Site visits must be requested through the Contracting Officer and if possible, site visits will be allowed on a case by case basis as many of these FOBs/COPs are still under construction and safety is of concern
18. Is the Government providng space on the FOB/COP to build an LSA for its LN employees? YES
19. What volume should offerors include for DBA? 4% of the estimated cost
20. Offeror assumes that if its receiving financial institutions currency is U.S. Dollars then payments will be made in U.S. Dollars? YES
21. What is the total number of personnel that the offerors are required to quote for? 43 Guards, 3 shift supervisors, 1 Site Manager
22. Is the resulting contract resulting from RFP a performance based acquisition per FAR Subpart 36.6? YES
23. What is the name of the incumbent contractor? There is no incumbent, this is a brand new COP
24. Are offerors required to submit proof of DBA insurance with their proposals? NO
25. Is the Government going to provide space for the staging of a kitchen facility? YES
26. The offeror assumes that the Government is providing billeting for all personnel for this contract? CORRECT