The work shall include the provision and installation of all structural, electrical, and equipment, materials and devices as indicated on the drawings and/or as specified herein, including but not limited to: Complete removal of the existing Aquia Waste Water Treatment Plant Service Motor Control Center “MCC1”. The equipment removal includes locating and identifying all existing 480 volt and 120/208 volt circuits. All existing 480 volt and 120/208 volt circuits shall be extended and rerouted to new 480 volt and 120/208 volt panelboards provided under this Contract. Re-route and extend the existing circuits to the existing Control Building (labeled “Office Building”), and Maintenance Building. Removal of the existing 1,600 amp bus duct feeding Service Motor Control Center MCC1 from the main service switchboard, including the associated cable feeders. Provide a new 480 volt, 600 amp feeder to feed the new 480 volt panelboard from the existing circuit breaker which fed MCC1.