The principal items of work and approximate quantities are: Overburden Drilling and Casing, Steel or PVC, 10,203 L.F. Four-Inch (4") Air Rotary Drilling, 33,942 L.F. Furnishing and Installing Four-Inch (4") Nominal Steel or PVC Injection Casing, 32,224 L.F. Supply and Delivery, Mixing and Injection of Grout Material - Cement, 5,045 TON Supply and Delivery, Mixing and Injection of Grout Material - Fly Ash, 29,522 DRY TON Supply and Delivery, Mixing and Injection of Grout Material - Stone (AASHTO No. 57), 20 TON Supply and Delivery, Mixing and Injection of Grout Material - Sand (Type A), 17,892 DRY TON Injection Site Preparation and Site Restoration, 497 EACH Beginning on the Issue Date, free copies of bid documents can be obtained by going to www.BidExpress.com, PA Department of Environmental Protection.