Federal Contract Opportunity

Last Updated on 29 May 2025 at 8 PM
Solicitation
Loveland Colorado

Y--Yellowtail Switchyard DCS Phase I Pre-Fabricated Building and Construction

Details

Solicitation ID 89503225BWA000069
Posted Date 29 May 2025 at 8 PM
Response Date 25 Jul 2025 at 8 PM
NAICS Category
Product Service Code
Set Aside No Set-Aside Used
Contracting Office Western-rocky Mountain Region
Agency Department Of Energy
Location Loveland Colorado United states 80538

Possible Bidders

National Industries For The Blind

Wayne Earth city Alexandria

L C Industries Incorporated

Hazlehurst Daytona beach Durham

Ww Grainger Incorporated

Cleveland Anchorage Lake forest Boston Atlanta Chula vista Saint louis Niles

Sign up to access Documents

Signup now
NOTE: This will be a Sealed Bidding Solicitation, all responses to this Invitation For Bid (IFB) shall be submitted via FedConnect ONLY. Email proposals WILL NOT be accepted.

The Western Area Power Administration (WAPA, Rocky Mountain Region (RMR) has a requirement for a Contractor to provide labor, materials, tools, equipment, transportation, and other resources necessary to complete this project.

Yellowtail Switchyard DCS Phase I priniciple components of work include demolishing of existing building, providing a new pre-fabricated building, complying with all applicable safety requirements contained in WAPA's Construction Standard 1 and OSHA Standards, replacing five (5) 230-kV power circuit breakers including their concrete foundations, rotating six (6) 115-kV power circuit breakers 180 degrees, replacing four (4) 115-kV power circuit breaker concrete foundations, removing six (6) pothead steel structures, removing two (2) disconnect switches (steel only), removing eighteen (18) bus poles and their foundations, removing two (2) lighting units and their foundations, removing two (2) disconnect switches and their foundations, removing one (1) 230-kV power circuit breaker and its foundation, removing two (2) single platforms, removing one (1) double platform, installing one (1) bus pole and its foundation, replacing twelve (12) 230-kV disconnecting switches, replacing two (2) 230-kV disconnecting switches with ground blades, installing one (1) 230-kV CCVT and its foundation, installing a prefabricated control building and associated equipment, material and foundations.