Federal Contract Opportunity

Last Updated on 25 Jun 2025 at 9 PM
Solicitation
La place Louisiana

West Shore Lake Pontchartrain WSLP 114

Details

Solicitation ID W912P825B0024
Posted Date 25 Jun 2025 at 9 PM
Response Date 08 Jul 2025 at 2 PM
NAICS Category
Product Service Code
Set Aside No Set-Aside Used
Contracting Office W07v Endist N Orleans
Agency Department Of Defense
Location La place Louisiana United states 70068

Possible Bidders

Amerisourcebergen Drug Corporation

Wayne Chesterbrook Malvern Conshohocken

Cardinal Health Incorporated

Shawnee mission Dublin Phoenix El paso

Amerisourcebergen Drug Corporation

Wayne Chesterbrook Malvern Conshohocken

Amerisourcebergen Drug Corporation

Wayne Chesterbrook Malvern Conshohocken

Amerisourcebergen Drug Corporation

Wayne Chesterbrook Malvern Conshohocken

Sign up to access Documents

Signup now

Amendment 0006: Please see amendment 0006 in the attachments.

Amendment 0005: Please see amendment 0005 in the attachments. Bid opening date has been re-established. 

Amendment 0004: Please see amendment 0004 in the amendment. Please note the bid opening date will be re-established in a future modification. 

Amendment 0003: Bid opening on 20 May 2025 at 10:00 a.m. CST has been temporarily postponed and a new bid opening date w ill be established in a forthcoming amendment. Please see amendment 0003 in the attachments.

Amendment 0002: Please see amendment 0002 in the attachments. 

Amendment 0001: Please see amendment 0001 in the attachments. 

Edit: This notice is edited to add WSLP_114_Signed Submittal Drawings-4 of 4

The U.S. Army Corps of Engineers - New Orleans District is issuing a Solicitation for Reserve Relief & I-55 Pump Stations and Drainage Structures, WSLP-114. 

This requirement is unrestricted under invitation for bid W912P825B0024. 

It is being procured as a firm fixed price under FAR part 14, Sealed Bidding. The designated NAICS code is 237990. 


The work consists of clearing and grubbing; pump station and associated construction, drainage structure construction, floodwall
construction (including braced floodwall and floodwall construction adjacent to and underneath an elevated highway); stop log construction, wingwall construction, placement of steel sheet piling, H-piling, pipe piles, precast/prestressed concrete piles, geotextile, geogrid, grouted riprap; installation of metal ladders, stairs, cat walk, and railings; installation of vertical wick drains and horizontal strip drains; stone and bedding construction; slide gates and hoist; precast concrete bridge, steel vehicular swing type flood gate, navigation gate and draw bridge; excavation and embankment placement; miscellaneous metal work, painting, turf establishment; chain link fencing, surfacing, structural excavation and backfill; electrical work; pluming; installation cybersecurity for control systems; construction of temporary retaining structures and dewatering, and other related incidental work.


The Rough Order of Magnitude of construction is betw een $250M - $500M. Questions are due NLT 26 March 2025 @ 2:00 PM CST.