Amendment 0005 is being issued to provide answers to questions received and to change the Period of Performance to October 01, 2025, to May 01, 2026, as originally submitted.
1. We are interpreting the drydock stability section to mean stability calculations in accordance with SFLC Standard Spec 8634 Appendix A. Are there further stability calculations needed? Correct, Only 8634 Appendix A.
2. Does the vessel have a trim & stability booklet that can be shared? Yes, Attachments 16 and 17.
3. Is there a GHS geometry file available? If not, is there a lines plan and tank plan available? Lines plan is attached (See Attachment 18 D105-01-1 Lines and Offsets). A hecsalv .sh2 geometry can be provided following the award if needed.